London Array wind farm

177 concrete platforms
620 tons of steel

Scope of works

Installation of reinforcement, carpentry works, prefabrication of reinforcing steel, installation of platforms, preparing and securing cargo for sea transport

Manpower

STEEL FIXERS, CARPENTERS, WELDERS, ELECTRICIANS AND CRANE OPERATORS 50
STEEL YARD EMPLOYEES 25

Supervision

Customer

Masdar & DONG Energy & E.ON Climate & Renewables UK

Main contractor

Bilfinger Berger GmbH
2011 -
2012

Our portfolio – projects we have completed so far:

Infrastructure 24
Offshore & Marine 17
Structures 12