Preparation and installation of reinforcing steel
The project completed in Świnoujście was a strategic investment. In the case of this project, we were responsible for the prefabrication of reinforcing steel and we participated in the reinforcement of walls of TK 2011 and TK 2012 tanks on the LNG Terminal construction site.
The diameter of each of the tanks is 80 meters and each can store up to 160,000 m3 of liquified gas. The delivery of reinforcing steel as well as other works were carried out 24 hours a day using slipform shuttering method.
The average rate for the erection of walls was 2 meters per day. This allowed us to complete two 40 meters high tanks in two months.