LNG Terminal in Świnoujście

4,000 tons of steel
4,500 Lenton joints

Scope of works

Preparation and installation of reinforcing steel

Manpower

STEEL FIXERS 43
STEEL YARD EMPLOYEES 25

Supervision

Customer

Polskie LNG S.A.

Main contractor

Hydrobudowa PBG,
Uniserv SA
2011 -
2012

Two tanks with
liquified gas

The project completed in Świnoujście was a strategic investment. In the case of this project, we were responsible for the prefabrication of reinforcing steel and we participated in the reinforcement of walls of TK 2011 and TK 2012 tanks on the LNG Terminal construction site.

The diameter of each of the tanks is 80 meters and each can store up to 160,000 m3 of liquified gas. The delivery of reinforcing steel as well as other works were carried out 24 hours a day using slipform shuttering method.

 

Flexible working hours and
completion within the specified time-frame

The average rate for the erection of walls was 2 meters per day. This allowed us to complete two 40 meters high tanks in two months.