Walls prefabrication – Arm-Tec

June 2016-October 2016

SCOPE OF WORKS

Reinforcement assembly, concrete casting, forklift.

Manpower:

  • steel fixers
  • driver
  • engineer
  • welder

Supervision

Customer

Arm-Tec

Main contractor

The project was about to construct hundreds of reinforced concrete walls for bus bays in Copenhagen.

GS Seacon supported prefabrication process by steel-fixing and casting. Prefabrication took place in Arslev – Arm Tec fabrication yard.

Our portfolio – projects we have completed so far:

Infrastructure 24
Offshore & Marine 17
Structures 12